Readiness review
Close critical prerequisites and assign responsibilities.
BOYUN Industrial Filtration Solutions – Ceramic Vacuum Disc Filter
Understand BOYUN’s installation guidance, commissioning checks, operator training and start-up support for vacuum and ceramic disc filtration systems.

The contract should distinguish BOYUN supervision or guidance from installation labor, lifting, utilities, consumables, permits and plant operations supplied by the customer or other contractors.
| Phase | BOYUN support when contracted | Customer/site preparation |
|---|---|---|
| Before installation | Review current drawings, sequence and critical interfaces. | Complete civil work, access, storage, lifting plan and qualified installation team. |
| Mechanical completion | Review alignment, assembly, lubrication and connection checklists. | Finish erection, piping, electrical work, guarding, punch list and statutory checks. |
| Cold commissioning | Support rotation, valve, instrument, interlock and utility checks. | Provide authorized operators, safe utilities and completed pre-startup approvals. |
| Wet commissioning | Support controlled introduction of water and slurry and operating adjustment. | Provide stable feed, downstream availability, sampling and laboratory support. |
| Handover | Review records, training and outstanding actions. | Accept deliverables, close punch items and own routine operation. |
Stop the equipment and isolate all hazardous energy that can cause rotation, vacuum, pressure, stored mechanical movement, electrical energization or chemical exposure. Follow the site lockout and permit procedure; inspection and maintenance must be performed only by authorized personnel.
Confirm readiness before travel, remote session or first rotation.
The actual commissioning plan follows the supplied equipment, site rules and contract.
Close critical prerequisites and assign responsibilities.
Confirm assembly, levels, clearances, lubrication and connections.
Test rotation, drives, valves, instruments and interlocks.
Introduce water and slurry under controlled conditions.
Measure agreed criteria, record settings and train the team.
Record feed conditions, stabilized period, sampling points, laboratory methods, calculation formulas, exclusions and responsibilities. Results outside the agreed feed envelope should trigger engineering review, not an improvised guarantee.
Feed solids, PSD, temperature, throughput and chemistry must match the agreed test basis.
Use identified sample points, frequency, preparation and laboratory procedures.
Close operating settings, maintenance actions, spare parts and open items.
Use the connected engineering and service pages before commissioning.
These answers support project preparation; the final recommendation depends on the actual duty.
Share the feed, throughput, operating target and site constraints. BOYUN will identify missing information and recommend testing, sizing or the appropriate equipment scope.